Home Systems Guide · No. 6 · Theory guide, set v2 · draft 1

Solar & Battery Storage

How much array a roof admits once the fire code has taken its share, how orientation, string grouping and inverter size turn it into energy, what a kilowatt-hour is worth under California's net billing tariff by the path it takes, how a battery's energy and power limits shape backup, and which interconnection route and location the code leaves open.

Refer to the following guides for concepts:

Applied to this house: House Project Guide, chapter 6

DepthModerate
Governing code2025 CEC (2023 NEC), 2025 CRC and CFC, from 1 January 2026
TariffCPUC net billing tariff; PG&E E-ELEC as reference
Reference systemGable roof at 4:12; 11.5 kW, 13.5 kWh storage inverter
VersionSet v2 draft 1 · 2026-10-23

Read this first

  1. The fire code sets the array, and its ridge setback depends on the coverage it produces, so where a layout can straddle 33% the compliant maximum sits just under the threshold rather than at the largest layout the roof holds. Part 1
  2. On a low-pitch gable the two planes together behave almost like one horizontal array, so ridge orientation decides which plane to fill first and barely changes a two-plane total. Part 2
  3. Two differently lit groups in series on one tracker lose up to a third of their power, which makes independent trackers, not inverter size, the specification for a split array. Part 3
  4. Under net billing a kilowatt-hour is worth four to seven times more used or stored than exported, so self-consumption, not annual production, is what the array is valued on. Part 4
  5. Against direct use, a battery earns only when the peak-to-off-peak price ratio exceeds the inverse of its marginal efficiency: a wide margin in summer, and in winter a margin within the uncertainty of the inputs. Part 4
  6. Backup fails on power and on energy independently: one 11.5 kW unit cannot run two large loads at once at any state of charge. Part 5
  7. The busbar rule gates only one of three interconnection routes; under a power control system the bus rating sets the allowed setting instead of the source size. Part 6
  8. Where the battery may go is set by aggregate energy limits by location, and within those limits by heat, noise and working space. Part 7
Decisions this guide informs
DecisionDepends onTreated in
D1 Array extent: which planes, how many modules, in which orientationRoof plan and pitch; ridge orientation; pathways and the coverage threshold; roofs below escape openings; structure and roof coveringParts 1, 2, 7
D2 Inverter architecture and string groupingPlanes and shading; tracker count and limits; coupling efficiency; rapid-shutdown methodParts 3, 4, 8
D3 Storage energy, and the job it is bought forEvening load; tariff spread; marginal efficiency; competing thermal storesParts 4, 5
D4 Backup scope: whole house, managed, or critical loadsInverter continuous rating; the load stack; which loads can be shed; service arrangementPart 5
D5 Interconnection routeBusbar and main ratings; power control listing and acceptance; service arrangement and supply-side accessPart 6
D6 Equipment location and mountingAggregate limits by location; separations; heat; fan noise; working space; anchoragePart 7
Table 1 Which part treats which component
PartArrayInverterBattery
1 · RoofPathways, setbacks, module fit——
2 · ProductionOrientation, tilt, yield——
3 · Strings and invertersString length, groupingTrackers, DC:AC ratio, clipping—
4 · ValueSelf-consumptionConversion lossesArbitrage, break-even
5 · Storage and backupRecharge in an outageContinuous ratingEnergy, autonomy
6 · Interconnection—Route, power controlIslanding equipment
7 · Siting and structureAttachment loadsLocationLocation limits, heat, noise
8 · Code and the utilityRapid shutdown, permitDisconnects, markingListing, fire code

Table 1 maps the parts to the three components. Subsections that cover one component carry an Applies to tag. An Informs tag marks the subsections behind each decision above.

1 · Roof: what the fire code leaves for modules

Bottom line. The usable roof is a code result, not a geometric one: a pathway from eave to ridge and a clear band at the ridge take 14–21% of each plane, and with installer margins and whole-module rounding 36–39% of the plan carries no module.

Pathways and a ridge setback reserve fire-service access

ArrayInverterBattery

Informs D1

The 2025 CRC (R329.6, numbered R324.6 in the 2022 edition) keeps roofs workable for fire fighters. It requires at least two 36 in pathways from the lowest roof edge to the ridge on separate roof planes, one on the street or driveway side, and a 36 in pathway on or next to every plane that carries modules. At a horizontal ridge it requires a clear setback on both sides: 18 in where the array covers no more than 33% of the plan-view roof area, 36 in above that. With an NFPA 13D sprinkler system the thresholds become 66% and the same widths. Roofs of 2:12 or less are exempt. Modules may not sit on any roof below an emergency escape and rescue opening, and a 36 in pathway must reach the opening (Windows & Doors · Escape openings).

Figure 1 draws the reference gable: a 40 × 35 ft footprint (the spec's 1,400 sf ceiling) with 1.5 ft eaves and 1 ft rakes, 42 × 38 ft in plan, 1,596 sf. Each plane is 42 ft wide and 20.0 ft from eave to ridge along the slope. A 6 in margin at the eave and the far rake is installer practice for wind edge zones and access, not a code rule.

One plane of the reference gable with pathway, ridge setback and modulesA plane 42 ft along the ridge and 20.0 ft from eave to ridge along the slope, with a 36 in pathway at one rake, the ridge setback on both sides of the ridge, an eave margin, and four landscape rows of six modules.ridgeeave36 inpath18 in36 inother plane42 ft along the ridge20 ftto ridge
Figure 1. Fire-service access removes area in fixed dimensions: depth at the ridge and width at each pathway. One plane of the reference gable; the other mirrors it across the ridge. Teal is the pathway required on each array plane, a reserved area rather than a grade; amber is the ridge setback, solid for 18 in on each side and dashed for the additional band above 33% coverage; green is modules, here landscape at the 36 in setback. Eave and rake margins are installer practice.

The ridge setback depends on the coverage it produces

ArrayInverterBattery

Informs D1

The setback is chosen by the coverage, and the coverage is a result of the setback. Table 2 fits a 430 W module class (1,762 × 1,134 mm, 20.4 sf in plan at 4:12) to one plane. At the 18 in setback, portrait fits 3 rows of 10, 30 modules, which cover 38% of the roof's plan area; that exceeds 33%, which requires the 36 in setback, which leaves room for only 2 rows, 20 modules. The code tests the layout as designed, so the compliant maximum is the largest layout that stays under 33%: 25 modules (510 sf of 527 allowed), 10.75 kW. Removing the 5 modules that cross the threshold avoids losing 10 (Figure 2).

Module orientation changes the result only in one branch. Landscape fits 4 rows of 6 at either setback, because four landscape rows (15.1 ft) fit inside both the 18.0 ft and the 16.5 ft depth budgets; three portrait rows need 17.5 ft and fit only the first. Arrays on both planes cover more than 33% together, so both take the 36 in setback; the two-plane maximum is 48 modules in landscape, 20.64 kW, covering 61% of the plan.

Table 2 Modules per plane by ridge setback and module orientation: the 18 in portrait layout fails its own threshold
Ridge setbackOrientationRows × columnsModulesPlan coverageComplies
18 inPortrait3 × 103038%No: over 33%
18 inLandscape4 × 62431%Yes
36 inPortrait2 × 102026%Yes
36 inLandscape4 × 62431%Yes
Modules on one plane by layoutThe 30-module portrait layout exceeds 33% coverage and is non-compliant; trimming it to 25 keeps the 18 in setback.18 in, portrait, 303018 in, portrait, trimmed to 252518 in, landscape2436 in, portrait2036 in, landscape240816243233% of plan
Figure 2. Crossing the coverage threshold costs more modules than it adds: the 30-module layout (red) forces the wider setback, where portrait holds 20. Green layouts comply. The dashed line is the largest whole-module count under 33% of the plan area.

Two sensitivities matter. The four-row landscape result clears its depth budget by 17 in, so it survives a 12 in eave margin (48 modules on two planes) but not a deeper margin or a larger module. A hip roof of the same footprint has trapezoidal long planes whose rows shorten toward the ridge and short triangular planes that hold few modules, so the same coverage arithmetic gives fewer modules.

Watch out

A layout drawn to the 18 in setback and then filled is non-compliant if the filled layout passes 33%. The check is on the final module count in plan view, not on the setback assumed at the start.

2 · Production: orientation, tilt and the shape of the day

Bottom line. At a 4:12 pitch a plane facing east or west yields about 86% of a south plane and a north plane about 70%; the two planes of a gable together yield almost the same whichever way the ridge runs.

Annual yield is plane-of-array irradiance times a performance ratio

ArrayInverterBattery

Informs D1

E = P_DC × H_POA × PR

E annual AC energy, kWh · P_DC array rating at standard test conditions, kW · H_POA annual irradiation on the plane, kWh/m² · PR performance ratio, 0.75–0.85

a kilowatt of modules delivers its plane's yearly sunshine in kWh/m², less temperature, soiling, wiring and inverter losses.

A clear-sky geometric model at 37.4° N, weighted by typical monthly clearness for a coastal climate zone 3–4 reference, gives 1,938 kWh/m² a year on a south plane at 18.4°; with a performance ratio of 0.82 that is about 1,600 kWh per kW. Absolute yields vary ±10% with local fog and haze; the ratios between orientations, which the arguments here rest on, vary by about ±0.03 against an hourly simulation. Figure 3 and Table 3 give the ratios by facing and tilt.

Annual yield relative to a south plane at the reference tilt, by azimuthThree curves for tilts of 10, 18.4 and 33.7 degrees, peaking at south. At low tilt the curve is flat; at higher tilt north-facing yield falls steeply.0.40.60.81.0NESWNDirection the plane facessouth at 4:12 = 1.08:12 (33.7°)4:12, north 0.702:12 (10°)
Figure 3. At low tilt orientation costs less than intuition from steep roofs suggests: at 4:12 (dark teal) a north plane keeps 70% of the south plane's yield, at 8:12 (dashed) only 53%. Curves are relative to the south plane at 4:12, a neutral quantity.
Table 3 Annual yield relative to a south plane at 4:12, by tilt and facing: north planes lose most as the roof steepens
PitchTiltSouthEast or westNorth
Flat0.0°0.890.890.89
2:1210.0°0.960.880.80
4:1218.4°1.000.860.70
6:1226.6°1.020.830.61
8:1233.7°1.030.800.53
12:1245.0°1.010.760.41

The two planes of a gable sum to a near-horizontal array

ArrayInverterBattery

Informs D1

cos i_A + cos i_B = 2 · cos β · sin α_s (both planes sunlit)

i angle of incidence on each plane · β tilt · α_s solar altitude

for planes facing opposite ways at the same tilt, the azimuth terms cancel, leaving twice a horizontal surface scaled by the cosine of the tilt.

Opposite planes tilted at β see beam irradiance whose azimuth-dependent terms are equal and opposite, so whenever the sun is above both planes their sum is fixed by the sun's altitude alone. At 4:12 a plane is in its own shade only when the sun is below 18° behind it, near sunrise and sunset or at low winter sun. The result: a full two-plane array produces almost the same energy and the same daily shape whether the ridge runs east–west or north–south (Figure 4). With 10.32 kW on each plane, south plus north gives 28,000 kWh a year and east plus west 28,000 kWh, within 1%.

Clear equinox day output of single planes and of plane pairsSingle planes facing south, north, east and west have very different shapes; the south-plus-north and east-plus-west pairs nearly coincide.02505007501000681012141618Solar time, hW/m² on the planesouthnortheastwestpairs: S+N solid, E+W dashed
Figure 4. Single planes differ in size and timing; opposite pairs coincide. Thin light teal lines are single planes; the thick line is the mean of south and north, the dashed line the mean of east and west. Clear-sky model, 20 March.

Ridge orientation still matters for a partial array. With one plane filled, the south plane yields 17,000 kWh and an east or west plane 15,000 kWh, 14% less. Adding the second plane, which also costs a module on the first, adds 11,000 kWh a year to a south plane and 13,000 kWh to an east or west plane, a marginal yield of 1,100–1,400 kWh per added kW against 1,600 for a south plane alone. These are statements on two axes: the two-plane array produces the most energy, and its second plane returns less per installed kilowatt than the first (Table 4).

Annual production by roof case
Table 4 Annual production at the compliant maxima of Part 1: the pair totals nearly coincide
Roof caseModuleskW DCAnnual kWhkWh per kW
One plane, south2510.7517,0001,600
One plane, east or west2510.7515,0001,400
Two planes, south and north4820.6428,0001,400
Two planes, east and west4820.6428,0001,400

3 · Strings and inverters: grouping, voltage and clipping

Bottom line. A tracker imposes one operating point on everything wired to it, so modules in different light in one series string belong on different trackers; string length is bounded by cold-morning voltage, and the inverter's AC rating clips what the array produces above it.

Series mismatch on one tracker peaks at a third of the output

ArrayInverterBattery

Informs D2

Loss(r) = 1 − max(2r, 1) ÷ (1 + r), r = G_weak ÷ G_strong ≤ 1

two equal groups of modules in series on one tracker; current proportional to irradiance, voltage nearly constant

the tracker either runs both groups at the weak group's current or bypasses the weak group; it keeps the better of the two, and the shortfall is largest when one group sees half the light of the other.

A series string carries one current. With two groups at different irradiance, the maximum power point tracker can run the string at the weak group's current with both conducting, or at the strong group's current with the weak group bypassed by its diodes. The loss peaks at 33% when r = 0.5 (Figure 5). A south and a north plane at 4:12 pass through r = 0.5 on most days, at hours of high production; the loss never goes negative. On separate trackers it is zero. Two strings of equal length in parallel on one tracker are a different case: maximum-power voltage barely changes with irradiance, so a parallel east and west pair loses a few percent at most, typically from temperature differences.

Mismatch loss when two differently lit groups share one trackerLoss rises linearly to 33% at an irradiance ratio of 0.5, then falls to zero at a ratio of 1.0%10%20%30%40%0.000.250.500.751.00Irradiance ratio of the weaker group, rPower lostr = 0.5, loss 33%
Figure 5. The kink at r = 0.5 is where the tracker switches between running both groups and bypassing the weaker one. Red is the loss. The model ignores the small fall of module voltage at low light and bypass diodes on thirds of a module, which round the corner.

Shade from a vent, a chimney or a neighbor's roof is the same problem inside one string. Module-level electronics (microinverters or optimizers) remove it by construction; string inverters remove it by allocation, one orientation and one shading pattern per tracker. The specification that matters for a split array is the count of independent trackers and their current limits.

String length is bounded by cold-morning voltage and the tracking window

ArrayInverterBattery

Informs D2

V_oc,max = V_oc × [1 + β_Voc × (T_min − 25)]; n_max = floor(V_max,inverter ÷ V_oc,max)

V_oc open-circuit voltage at 25 °C · β_Voc its temperature coefficient, about −0.25 to −0.30 %/°C · T_min extreme minimum design temperature, °C

a cold module at sunrise has its highest voltage, and the string's total must stay below what the inverter is rated for.

690.7(A) takes the module manufacturer's coefficient with the ASHRAE extreme annual mean minimum for the site; coastal California sites sit near −2 to 0 °C. For the reference module and a 550 V, 60–480 V inverter, the longest string is 13 modules and the practical shortest three (Figure 6). Currents are checked separately: the circuit current is 1.25 × I_sc (690.8(A)), and a tracker publishes both the array short-circuit current it accepts and the operating current above which it limits output.

String limits for the reference module

V_oc 39.0 V and −0.25 %/°C at −2 °C give 41.6 V per module, so 550 V ÷ 41.6 V admits 13 in series; cold V_mp of 35.1 V keeps 13 modules under the 480 V tracking ceiling. At a 65 °C cell V_mp falls to 28.6 V, so three modules (86 V) is the practical minimum above the 60 V floor. A 13.9 A I_sc gives a circuit current of 17.4 A; a 13.2 A I_mp on a 13 A tracker limits output by about 1.5% at peak, a performance loss rather than a code failure, while an array I_sc above the tracker's short-circuit rating is outside its listing.

String voltage by number of modules against inverter limitsFor 3 to 14 modules, cold open-circuit voltage and hot maximum-power voltage; limits at 550 V input and a 60 to 480 V tracking window.010020030040050060034567891011121314Modules in seriesString voltage, V550 V input maximum480 V tracking ceiling60 V tracking floor
Figure 6. Thirteen modules is the longest string. Each bar spans the string's operating range, from hot V_mp (bottom) to cold V_oc (top). Green strings stay under the 550 V input maximum; red ones exceed it. Dashed teal lines are the inverter's limits.

Rapid shutdown decides where electronics sit on the roof

ArrayInverterBattery

Informs D2

690.12 requires conductors on a building to drop to safe levels within 30 seconds of initiation, so a fire fighter on the roof is not on energized DC. Outside the array boundary, 1 ft around the array, conductors fall to 30 V. Inside it, the 2023 NEC accepts a PV hazard control system listed to UL 3741, or controlled conductors at 80 V or less. A 13-module string runs about 541 V cold, so either route needs devices on the roof: module-level electronics (a microinverter or optimizer behind each module), or mid-circuit interrupters that split each string into segments, listed with the inverter as a hazard control system. Microinverters have no DC array to shut down; string inverters keep the conversion on the ground and add one device per few modules. The choice is where the roof electronics sit, not whether there are any.

A DC:AC ratio above one trades clipped peaks for fuller shoulders

ArrayInverterBattery

Informs D2

Arrays are rated at standard test conditions they rarely reach: at a 45 °C cell, with soiling and wiring losses, clear-sky noon output runs near 86% of nameplate after the inverter. Oversizing the array against the inverter's AC rating fills the morning and afternoon at the cost of clipping the noon peak. Figure 7 shows the clipped share of annual output by DC:AC ratio. A split array, whose two planes peak at different hours and whose sum is flatter, clips about half as much as the same array facing south.

Annual clipped share of AC output by DC:AC ratioAll-south and split-plane arrays; clipping begins near 1.3 to 1.5 and reaches 9 to 13% at 2.0.0%5%10%15%0.81.01.21.41.61.82.0DC:AC ratioShare of annual output clippedone plane 0.93two planes 1.79all southsplit planes
Figure 7. A split array clips less at every ratio because its combined profile is flatter. Dark teal is the array facing south; dashed teal is the same array split across opposite planes (east–west gives the same curve). Vertical lines mark the Part 1 maxima on one 11.5 kW inverter. Model of hourly clear-sky irradiance scaled by monthly clearness; real annual clipping on hazy days is lower.

The two-plane maximum, 20.6 kW on an 11.5 kW inverter, is a ratio of 1.79; it clips about 5% of annual output and exceeds the 20 kW DC input of a single 11.5 kW storage-inverter class unit. Either a second inverter or a smaller array follows from the equipment, not from the roof.

4 · Value: what a kilowatt-hour is worth by the path it takes

Bottom line. Under net billing an exported kilowatt-hour earns the utility's avoided cost, a few cents, while one used or stored displaces a retail time-of-use price; a battery is a device for moving energy across a price spread, and it earns only when the spread exceeds its losses.

Coupling decides how many conversions a stored kilowatt-hour makes

Informs D2 D3

Solar reaches a load through a chain of conversions, each quoted against a different denominator (Figure 8). In a DC-coupled hybrid the array charges the battery on the DC side and one inverter serves the house: a class-typical unit quotes 97.5% from solar to the house and 89% from solar through the battery to the house. In an AC-coupled system the PV inverter converts to AC and the battery converts back and forth again; its battery round trip of about 88.5% comes on top of the PV inverter. The figure that governs a storage decision is the marginal one: the stored path against delivering the same energy now.

η_marg = η_solar→battery→home ÷ η_solar→home

DC-coupled 0.89 ÷ 0.975 = 0.913 · AC-coupled: the battery's AC round trip, about 0.885

the share of a kilowatt-hour that survives being stored instead of used at once; the PV inverter's loss is common to both paths and cancels.

DC-coupled and AC-coupled conversion chainsDC-coupled: array to battery on DC, one inverter to the house. AC-coupled: PV inverter to AC, battery inverter converts to DC and back.DC-coupledArray (DC)Battery (DC)Hybrid inverterHouse (AC)stored path 89% · direct 97.5%AC-coupledArray (DC)PV inverterBattery inverterBattery (DC)House (AC)stored path 86% · direct 97.5%
Figure 8. A DC-coupled battery charges before the only inversion; an AC-coupled battery adds a rectification and a second inversion. Teal notes give class-typical efficiencies from solar to the house by each path. The AC-coupled system's advantage is independence: array and battery are sized, sourced and replaced separately.

The same kilowatt-hour is worth four to seven times more used or stored than exported

Informs D3

The CPUC's net billing tariff (D.22-12-056, for applications from 15 April 2023) credits exports at hourly values from the Avoided Cost Calculator, locked for nine years from the interconnection year, and requires residential customers to take a time-of-use rate (E-ELEC for PG&E). The reference prices in Table 5 are PG&E's E-ELEC bundled rates from 1 March 2026; a customer of a community choice aggregator pays the same delivery charges with the aggregator's generation rate. Exports are taken at a blended midday credit of 6.0¢ plus the 0.88¢ adder for 2026 interconnections.

Table 5 Reference time-of-use prices and export credit, ¢/kWh: the summer peak is 1.7 times off-peak, the winter peak 1.1 times
PeriodHoursSummer (Jun–Sep)Winter (Oct–May)
Off-peakMidnight–3 p.m.33.428.5
Partial peak3–4 p.m., 9 p.m.–midnight39.029.9
Peak4–9 p.m.55.232.1
Export credit, blended midday—6.886.88

E-ELEC also carries a base services charge of about $0.79 a day from March 2026, which no generation offsets. Rates scale; the ratios carry the argument.

Applying the efficiencies, a DC kilowatt-hour is worth 6.7¢ exported, 32.5¢ used as it is generated and 49.1¢ stored and discharged into the summer peak (Figure 9). In winter the stored value falls to 28.5¢ against 27.8¢ used directly: storage beats immediate use by 16.6¢ in summer and 0.8¢ in winter. Against export it wins by 42¢ and 22¢. Non-bypassable charges apply to every imported kilowatt-hour under net billing and export credits cannot offset them, which raises the value of using solar on site above the retail comparison.

Value of one kilowatt-hour of solar by path and seasonExported about 6.7 cents in both seasons; used directly 32.5 summer and 27.8 winter; stored to the peak 49.1 summer and 28.5 winter.01020304050¢ per kWh of DC solar6.76.7Exported32.527.8Used as generated49.128.5Stored to the peaksummerwinter
Figure 9. Storing beats using directly by 17¢ in summer and by less than a cent in winter, because the winter peak is only 13% above off-peak. Bars are a neutral magnitude; the two shades are seasons.

Storage earns when the price ratio exceeds the inverse of the marginal efficiency

ArrayInverterBattery

Informs D2 D3

P_peak ÷ P_off-peak > 1 ÷ η_marg

P prices of the hour the energy is used and the hour it was generated

moving a kilowatt-hour from midday to evening pays only if the evening price exceeds the midday price by more than the storage loss.

The break-even ratio is 1.096 for the DC-coupled class and 1.130 for the AC-coupled class (Figure 10). The reference summer ratio, 1.66, clears both widely; the winter ratio, 1.126, clears the DC-coupled case by 2.8% and sits within 0.3% of the AC-coupled break-even, inside the uncertainty of the efficiencies. Against export, the comparison whenever the array has surplus, both clear by a factor of four or more. A few points of round-trip loss from aging or a cold battery move the winter case across the line; the summer and export cases do not move.

Break-even peak to off-peak price ratio against marginal storage efficiencyThe break-even curve 1 over efficiency falls from 1.25 at 0.80 to 1.0 at 1.0. The winter tariff ratio 1.126 lies above the DC-coupled break-even 1.095 and below the AC-coupled break-even 1.130.1.01.11.21.30.800.850.900.951.00Marginal efficiency of the stored path, η_margPeak ÷ off-peak pricewinter tariff ratio 1.126storage pays above the curve; summer ratio 1.66 is off the scalestorage loses money below the curveDC-coupled break-even 1.096AC-coupled break-even 1.130
Figure 10. A tariff ratio above the curve makes shifting a kilowatt-hour pay. The winter ratio (dashed) clears the DC-coupled break-even (green) and sits on the AC-coupled one (red), within the uncertainty of the inputs. The curve and the tariff line are neutral; the dots are graded against the winter case only.

Storage is sized against the evening load, not the daily total

ArrayInverterBattery

Informs D3

The quantity a battery displaces is the energy used in the peak window that could have come from a store, capped by the surplus available to fill it. Table 6 builds an all-electric reference demand of 16,000 kWh a year, 44 kWh a day. EV charging is scheduled off-peak by rate design and leaves the evening; with 30% of the rest in the 4–9 p.m. window, the addressable evening load is about 10 kWh a day, three quarters of one 13.5 kWh unit.

Reference all-electric demand build-up
Table 6 Reference annual electricity demand, all-electric house, kWh: heating and EV charging are the large terms
End useBasiskWh/yrShare
Space heatingUA 790 Btu/h·°F × 24 × 2,500 HDD ÷ 3,412 ÷ COP 3.54,00024%
Hot water60 gal/day at 120 °F from 58 °F, COP 3.01,1007%
Space coolingTypical, CZ 3–48005%
Lighting, plug loads, ERV, dehumidifierTypical for 2,300 sf5,50034%
Induction cookingTypical4002%
Clothes drying, resistanceTypical7004%
EV charging12,000 mi ÷ 3.5 mi/kWh × 1.103,80023%
Total16,000100%

Rows rounded. Heating uses the HVAC guide's reference UA with U-0.27 windows and degree-days at a 65 °F base without a balance-point correction, an upper bound. Typical rows are illustrative.

Value ≈ E_evening × Σ_seasons days × (V_stored − V_alternative)

V_alternative export (6.88¢ credited) when the array has surplus; direct use otherwise

each kilowatt-hour a day of evening load the battery covers earns the spread between its stored value and what the energy would otherwise have earned, every day of the season.

Each kilowatt-hour a day of evening load covered from stored surplus is worth about $105 a year against export at the reference prices, if the array has surplus to store every day of the year. In winter most arrays have little: a two-plane array's December output is roughly a third of its annual mean, close to the daytime load. Valued against export in summer and against direct use in winter, the figure is about $54 per kilowatt-hour a day, so the reference evening load gives about $550 rather than $1,100. Against direct use, the case where the array would otherwise have covered the load at once, the same kilowatt-hour earns $22 a year, almost all of it in summer. A second unit adds nothing to this line unless the evening load exceeds the first unit; its case is backup depth (Part 5).

Key point

A battery bought for bill savings is sized to the evening load; a battery bought for backup is sized to the outage load set. The two give opposite answers on whether a second unit pays.

A thermal store shifts its stored heat divided by the COP

Informs D3

Any load moved from evening into midday captures the same spread with no round-trip loss, but a thermal store shifts electricity at the heat pump's efficiency. Heating a 50 gal tank 20 °F above its setpoint at midday stores 2.4 kWh of heat, about 0.8 kWh of electricity at COP 3 (HVAC · Peak-hour draw). A 900 sf, 4 in heated slab stores 8,700 Btu per °F; a 3 °F swing is 7.6 kWh of heat, 2.2 kWh of electricity at COP 3.5, and only where the slab is insulated below and at its edge (Insulation · Heated slabs). Together they shift a few kilowatt-hours a day, a fraction of the evening load, and they cost nothing but control.

5 · Storage and backup: power, energy and scope

Bottom line. An islanded house runs out of power the instant demand exceeds the inverter's continuous rating and out of energy when the battery reaches its reserve; the first decides which loads may run, the second for how long.

Continuous rating decides which loads may run together

ArrayInverterBattery

Informs D4

The reference storage inverter delivers 11.5 kW continuously and starts motors up to 185 A locked rotor. Against the all-electric load stack in Electrical · Reference load stack, the charger alone equals it and the range nearly matches it; no two of the large loads in Figure 11 fit together. Whole-house backup on one unit energizes every circuit; it does not allow every load to run.

Large loads against one storage inverter's continuous outputCharger 11.5 kW, range 11 kW, heat pump 6 kW, supplementary heat 6 kW, dryer 5 kW, water heater element 4.5 kW, small loads about 2 kW, against an 11.5 kW rating.Charger, 48 A11.5 kWInduction range, full11.0 kWHeat pump, 25 A6.0 kWSupplementary heat6.0 kWClothes dryer5.0 kWWater heater element4.5 kWERV, circulators, dehumidifier1.3 kWRefrigeration, lighting, network0.8 kW02468101211.5 kW continuous
Figure 11. No two loads above half the rating can run at once. Red reaches the continuous rating alone; amber takes more than half of it; teal leaves room. Nameplates from the Electrical guide's reference stack, class-typical.

Three things close the gap: a second full unit, which doubles power and energy (a DC expansion pack adds energy only); automatic shedding of the charger, supplementary heat and dryer on loss of grid, which is a control architecture (Lighting · Load shedding); or occupants managing loads by hand. The first is equipment, the second controls, the third behavior.

Autonomy is usable energy divided by the mean load of the set kept on

ArrayInverterBattery

Informs D3 D4

t = E_usable ÷ P_mean

E_usable battery energy above its backup reserve, kWh · P_mean mean demand of the loads kept on, kW

hours of backup are stored energy over the average draw of whatever stays on.

With the full 13.5 kWh, no reserve kept and no solar input, the whole house without EV charging lasts about 9 h; essential loads alone last about 75 h (Figure 12). Heating dominates winter backup: at a mean December temperature difference of 20 °F the reference envelope's heat pump draws about 1.3 kW, which brings the essential set down to about 9 h, or 16 h with the setpoint lowered to halve it. With the array running, a two-plane array's December output of roughly a third of its annual daily mean recharges a unit on most days.

Backup hours on one 13.5 kWh unit by the loads kept onWhole house without EV 9 h; essential with winter heating 9 h; heating halved 16 h; essential only 75 h. A 13-hour winter night is the reference.Whole house, no EV charging9 hEssential loads with winter heating9 hEssential loads with heating set back to half16 hEssential loads only75 h0132040608013 h winter night
Figure 12. The load set kept on matters more than the battery's size. Green sets carry a 13-hour winter night without solar; red ones do not. The dashed line is that night, a reference. Load sets are typical; each bar scales inversely with its load.

Backup scope is a choice between wiring, controls and behavior

ArrayInverterBattery

Informs D4

Table 7 compares the four scopes by how each handles the power limit.

Table 7 Backup scope compared: whole-house islanding is cheapest to wire and needs either controls or discipline
ScopeHow it is builtPower limit handled byConsequences
Whole houseTransfer device islands every circuitOccupantsNo circuit moves; load-side or PCS route
Whole house, managedAs above; large loads shed on loss of gridControlsShed list and control wiring at rough-in
Critical loads panelChosen circuits on a backed-up panelWiringFixed autonomy; changes are alterations; second panel
Grid-tied, no islandingBill savings only—Simplest; no backup

6 · Interconnection: three routes and what gates each

Bottom line. Article 705 offers three ways to connect a source to a dwelling service, and each is gated by something different: a busbar rating, a listed control, or physical access ahead of the service disconnect.

Three Article 705 routes connect a source to the service

ArrayInverterBattery

Informs D5

Load side, 705.12. The source breaker lands on a panel bus. Under the 120% rule the largest backfeed breaker is 1.2 × bus − main, with the breaker at the opposite end and labeled (Electrical · Busbar backfeed): a 200 A bus with a 200 A main admits 40 A, below the 60 A a 48 A inverter needs; a 225 A bus with a 200 A main admits 70 A. The rule applies to every bus between the source and the service.

Power control, 705.13. A power control system listed to UL 1741 (PCS) limits the current a source can push onto a bus or conductor to a configured value, and the code then sizes that bus to the setting rather than to the source's full output. A storage inverter with a PCS listing can be set to export no more than the bus can take, or to discharge only to the house. Sources outside the control still meet 705.12 on their own.

Supply side, 705.11. The source connects between the meter and the service disconnect, where no panel bus is involved; the conductors and their overcurrent protection are sized to the source under 705.11. The tap point must be reachable, which the service arrangement decides. A supply-side source runs in parallel with the grid; to back up the house, an islanding device has to sit between the utility and both the tap and the loads.

Feeder, 705.12(A). Where a meter-main disconnect feeds an interior panel, the source may connect to the feeder between them, sized under 705.12(A) rather than against a bus (Electrical · Service arrangements).

Three interconnection routes on a one-line diagramLoad-side: source breaker on the panel bus, limited by the busbar rule. Power control: a listed controller limits source current onto the bus. Supply-side: tap between meter and service disconnect, ahead of any bus.705.12 load sidegated by busbar ratingMmainbus705.13 power controlgated by listing and settingMmainbus705.11 supply sidegated by tap accessMmainbussource1.2·bus − mainsourcePCSsourceno bus in the path
Figure 13. Each route steps around a different constraint. Amber marks the bus the load-side rule limits; the outlined breaker is the source breaker the rule sizes; the PCS (dashed) limits source current onto a bus; the supply-side tap joins ahead of the main, so no bus is in its path. Teal notes are code annotations.

Table 8 sets the three routes side by side.

Table 8 Interconnection routes compared: each is gated by something different
RouteGated byWhole-house backupDecided when
705.12 load sideBus and main ratings; breaker at the opposite end, labeledYes, with a transfer deviceThe panel is bought
705.13 power controlUL 1741 PCS listing; the setting; building department acceptance; other sources still meet 705.12YesThe inverter is chosen
705.11 supply sideAn accessible tap ahead of the service disconnect; conductor and overcurrent sizingOnly with separate islandingThe service arrangement is chosen

Which route is open is set by equipment chosen in the Electrical guide: the bus and main ratings and the service arrangement, including a storage gateway ahead of the load panels. Under a PCS the bus rating still bounds the setting. Where a gateway or transfer device becomes the service equipment, the bonding moves to it and the existing panel becomes a subpanel (Electrical · Grounding and bonding).

Every source is marked at the service and has its own disconnect

Informs D5

705.10 requires a permanent plaque or directory at each service equipment location showing every power source on the premises and its disconnect. 705.20 requires a disconnecting means for each source; 706.15 requires one for the storage system that opens all its conductors and can be locked open. Replacing service equipment also brings the outdoor emergency disconnect of 230.85, which on a house with storage identifies where the other sources are isolated (Electrical · Provisions engaged).

7 · Siting and structure: the roof, the wall and the garage

Bottom line. Wind uplift, not weight, sizes roof attachments; the battery's location is limited by aggregate energy per location class and then by heat, noise and working space.

Uplift, not weight, sizes roof attachments

ArrayInverterBattery

Informs D1 D6

The CRC (R329.4) requires the roof under an array to carry two load cases, dead load including the modules plus snow, and dead load without them plus roof live load or snow, and the array and its supports to resist the component and cladding wind loads of Table R301.2.1(1). Modules, rails and attachments weigh about 3.0 psf, a small addition to a tile roof's dead load (Framing · Area loads). Each attachment carries the loads on its tributary area, attachment spacing along the rail times the spacing between rails (Figure 14).

Uplift and dead load per attachment by spacingAt 30 psf net uplift and 3.0 psf dead load: 2 ft spacing 174 and 17 lb, 4 ft 348 and 35 lb, 6 ft 522 and 52 lb; 4 by 4 ft 480 and 48 lb.2 ft along the rail, rails 2.9 ft apart174 lb uplift · 17 lb dead4 ft along the rail, rails 2.9 ft apart348 lb uplift · 35 lb dead6 ft along the rail, rails 2.9 ft apart522 lb uplift · 52 lb dead4 ft along the rail, rails 4.0 ft apart480 lb uplift · 48 lb dead0200400600800
Figure 14. Each attachment resists about ten times its dead load in uplift. Bars are net uplift at 30 psf, a neutral quantity; labels add the dead load at 3.0 psf.

Net uplift on rooftop arrays near edges and corners runs 20–40 psf at the basic wind speeds of coastal California (ASCE 7 Chapter 29, typical); at 30 psf a 4 ft × 2.9 ft tributary area pulls 348 lb, and the screw has to develop it in the truss top chord rather than the sheathing. A fastener into a top chord is not a cut, but the truss manufacturer's limits on edge distance and spacing govern (Framing · No truss member is cut).

Verify

Expedited permit paths (the California Solar Permitting Guidebook, SolarAPP+) carry their own structural eligibility criteria for typical roofs; a design outside them, or a building department asking for analysis, needs the truss drawings and an engineer. The criteria are confirmed with the path used.

On a concrete tile roof the underlayment, not the tile, is the waterproofing. Tile hooks or flashed standoffs pass through it, and an array has to come off to replace it; felt underlayment of the 1985–2005 vintage is at or past its typical service life, which makes the roof and the array one decision.

Aggregate energy limits by location decide where storage may go

ArrayInverterBattery

Informs D6

The fire code (CFC 1207.11, carried into the 2025 CRC as R330, numbered R328 in 2022) caps an individual unit at 20 kWh, limits the total in each location class (Table 9) and on the property to 600 kWh; above the residential limits the full CFC 1207.1–1207.9 applies. Units are spaced 3 ft apart unless large-scale fire testing to UL 9540A supports closer spacing, which manufacturers of the 13.5 kWh class document. Storage is not permitted in sleeping rooms, closets opening into them or habitable space. In an attached garage the code adds protection where the unit is subject to vehicle damage, and a heat alarm interconnected with the smoke alarms where the garage stays at or below 100 °F (a heat detection system otherwise); the garage separation of R302.6, ½ in gypsum on the wall and ⅝ in Type X under habitable rooms above, is already required (Insulation · Garage boundary).

Table 9 Aggregate storage limits by location: three 13.5 kWh units fit any garage or exterior-wall location
LocationAggregate, kWhConditions
Utility closets, basements, storage or utility spaces inside the dwelling40Finished or noncombustible walls and ceilings
Attached garage80Separation from the dwelling per R302.6; vehicle impact protection; interconnected heat alarm
On or within 3 ft of an exterior wall100200 where the wall and eaves are noncombustible
Detached garage or accessory structure200600 at 10 ft or more from property lines and the dwelling
Outdoors on the ground2003 ft from property lines and the dwelling; 600 at 10 ft
Sleeping rooms, closets opening into them, habitable spaceNot permitted—

Values from the 2022 CFC Supplement Table 1207.11.4 as summarized by San Francisco Fire Department guidance; 2025 values under Verify below.

Verify

The 2025 CRC moved solar and storage provisions to R329 and R330 and added markings for building-integrated systems. The aggregate limits, the door-and-window separation and the garage detection rule are confirmed against the adopted CFC 1207.11 and CRC R330 before a location is chosen.

Heat, noise and anchorage separate the permitted locations

ArrayInverterBattery

Informs D6

The 13.5 kWh class operates to 50 °C and derates above 40 °C (104 °F). An uninsulated garage on a slab follows outdoor temperature with a lag and rarely exceeds 40 °C in a mild climate; a south- or west-facing exterior wall in afternoon sun can put an enclosure 15–20 °C above ambient during the hours of full discharge. Cooling fans run under 50 dBA at 1 m typically and 62 dBA at maximum, which coincides with peak discharge: about 52 dBA at 10 ft in free field, and the path into a room is the nearest window rather than the wall the unit hangs on (Soundproofing · Facade composite). Earlier residential editions also kept exterior units 3 ft from doors and windows into the dwelling.

Where component anchorage design applies (ASCE 7 §13.1.4 exempts some components of 400 lb or less mounted within 4 ft of the floor), a 287 lb wall-mounted unit at ground level in Seismic Design Category D sees a lateral design force governed by the code's minimum, 0.3 · S_DS · I_p · W_p, about 86 lb at S_DS 1.0 and I_p 1.0. Four structural screws into studs or blocking carry it easily; drywall does not. Where the wall is a braced wall panel its sheathing and nailing stay intact (Framing · Existing braced panels). Equipment working space in front of the gateway and disconnects competes with the panel's own clear space on a garage wall (Electrical · Working space).

Table 10 compares the permitted locations.

Table 10 Permitted locations compared on heat, noise and space: the garage and a shaded exterior wall are the usual choices
LocationHeat exposureNoise pathSpace and access
Attached garage wallLow; lags outdoor airThrough the garage–house wallShares wall with panel, charger, car
Shaded exterior wallLowest outdoorsNearest windowNo interior space
Sunlit south or west wallHigh at afternoon dischargeNearest windowOften the free wall
Interior utility spaceNoneInside the acoustic envelope40 kWh limit; floor area

8 · Code, permits and the utility

Which codes apply

Four parts of Title 24 govern a residential system, all from 1 January 2026: the California Electrical Code (Part 3, the 2023 NEC) for Articles 690, 705 and 706; the California Residential Code (Part 2.5) for roof access, structure and storage location; the California Fire Code (Part 9) for PV (1205) and storage (1207); and the Energy Code (Part 6). AB 130 (2025) holds residential building standards at this cycle until 1 June 2031, which bars most new local amendments; it does not reach the utility's interconnection rules, the CPUC tariff, or the discretion the code itself gives the fire code official to waive pathways where rooftop operations will not be used.

The Energy Code requires PV and battery readiness on newly constructed dwellings (§150.1(c)14, §150.0(s)); it imposes neither on an alteration that adds no floor area, and an interior remodel cannot trade array size against envelope performance. Because no code requires the system, it remains eligible for the net billing export adder, which excludes systems required by the building code.

Which provisions a residential solar and storage project engagesQuestions: modules on a roof; storage added; service equipment replaced; source on a panel bus. Each yes engages a set of provisions.Modules on a roof?yesR329.6 pathways · R329.4 loads and wind · 690.12 shutdownStorage added?yesR330 / CFC 1207.11 location limits · 706.15 disconnect · UL 9540 listingService equipment replaced?yes230.85 emergency disconnect · 250.50 electrodes · 705.10 directorySource on a panel bus?yes705.12 busbar rule, or 705.13 power control, or 705.11 supply sideIslanding for backup?yesTransfer equipment · bonding moves · panel becomes a subpanel
Figure 15. The questions are independent; each yes engages the provisions beside it in teal. A project that only adds modules on an existing service engages the first and fourth rows.

Figure 15 draws which provisions a project engages; Table 11 lists them.

Table 11 Provisions a residential solar and storage project engages, 2025 cycle
SectionRequirementWhy
CEC 690.7, 690.8Maximum system voltage at the coldest temperature; circuit current 1.25 × I_scEquipment and conductor ratings
CEC 690.12Rapid shutdown (Part 3); label at 690.12(D), formerly 690.56(C)Fire fighters on the roof
CEC 705.10–705.20Source directory at the service; one of three connection routes; a disconnect for each sourceUtility and fire service know every source
CEC 706.15Storage disconnect opening all conductors, lockable openIsolation for service
CRC R329.4, R329.6Roof load cases and wind; pathways, ridge setbacks, escape openingsRoof load; fire access
CRC R330; CFC 1207.11Unit and aggregate limits by location, spacing, garage protectionFire spread from batteries
Energy Code §150.1(c)14PV on new dwellings onlyNot engaged by an interior alteration

Permit, utility and covenants run as separate processes

The building department issues the electrical and building permits and inspects; the utility processes the Rule 21 interconnection application and grants permission to operate (PTO) after the building department's final. California requires cities and counties to offer automated online permitting for residential solar paired with storage (SB 379, 2022), on the standard path for a typical grid-tied system; a service change or a supply-side connection can move a project off it. The fire code official decides any waiver of pathways.

The tariff sets the system's size. Under net billing, estimated annual production may not exceed 150% of the most recent 12 months of usage; a customer whose usage has recently increased, or will, may use projected usage with an oversizing attestation, and the added load is expected within 12 months of PTO. For a house converting from gas, historic usage understates the all-electric load several times over: a 6,000 kWh history allows about 9,000 kWh of production against a reference all-electric demand of 16,000 kWh. The anticipated-load documentation (heat pump, water heater, range, charger) is what makes the larger system eligible; a 9,000 kWh history would allow 13,500 kWh, still short.

California's Solar Rights Act (Civil Code §714, and §4746 for common-interest developments) limits what a homeowners' association may require of a solar system to reasonable restrictions that do not significantly raise its cost or lower its performance, and sets a time for the association to act on an application. It does not exempt the system from the association's review.

Verify

The SB 379 scope (system size and storage limits for automated permits), the Civil Code §714 cost and performance thresholds, and the building department's reading of a power control setting are confirmed before a design depends on them. Federal tax treatment changed in 2025: the §25D credit for homeowner-owned systems ended for expenditures after 31 December 2025.

Where it goes wrong

  1. Array sized from gross roof area. Pathways, ridge setback, margins and whole modules leave over a third of the plan without modules, removed in specific dimensions (Part 1).
  2. The 33% threshold read as an input. A layout drawn to the 18 in setback and filled past 33% is non-compliant on every drawing that shows it (Part 1).
  3. Modules on a roof below an escape window. A porch, bay or garage roof under a bedroom window excludes modules there and needs a pathway to the window (Part 1).
  4. Two orientations in one series string. It presents as underperformance, not a fault; only a string-by-string comparison shows it (Part 3).
  5. A tracker's current limit read from the wrong line. Trackers publish both an operating current and a short-circuit limit, and some vary with the shutdown device used (Part 3; rapid shutdown).
  6. Round-trip efficiencies compared across denominators. A battery-only round trip and a solar-to-home-through-battery figure are not comparable; the winter case turns on the difference (Part 4).
  7. A thermal store counted in thermal kilowatt-hours. It shifts electricity at the heat pump's COP, about a third of its stored heat (Part 4).
  8. Whole-house backup assumed to run the whole house. One unit's continuous rating admits one large load at a time (Part 5).
  9. The busbar result taken as the interconnection answer, or a PCS assumed to cover sources it does not control (Part 6).
  10. A gateway installed without separating neutral and ground in the old panel, which the inspector checks when the bonding moves (Part 6).
  11. Attachments into sheathing or spaced for convenience. Uplift is developed in the truss top chord within the truss maker's fastening limits (Part 7).
  12. Interconnection applied for on historic gas-house usage, which caps the system near half the all-electric load unless anticipated load is documented (Part 8).

Reference

Glossary

ACC, ACC Plus
Avoided Cost Calculator: the CPUC model that sets hourly export values under net billing. ACC Plus is a temporary per-kWh adder for residential customers enrolling in the tariff's first five years.
Array boundary
690.12: the region 1 ft from the array in all directions, inside and outside which different rapid-shutdown limits apply.
DC:AC ratio
Array DC rating at standard test conditions divided by the inverter's continuous AC rating.
Clipping
Energy the array could produce but the inverter cannot pass because DC power exceeds its AC rating.
DC coupling, AC coupling
Whether the battery charges on the array's DC side through a shared inverter, or on the house's AC side through its own inverter.
Marginal efficiency
Term of this guide: solar-through-battery-to-home efficiency divided by solar-to-home efficiency.
MPPT
Maximum power point tracker: the control that sets one operating voltage for everything connected to it.
Net billing tariff (NBT)
California's tariff for new interconnections since 15 April 2023; PG&E markets it as the Solar Billing Plan.
PCS
Power control system: a listed control that limits source current on a bus or conductor (705.13).
Performance ratio
Annual AC energy divided by what the array's STC rating would deliver from the plane-of-array irradiation.
PTO
Permission to operate: the utility's authorization to energize a generating facility.
PVHCS
Photovoltaic hazard control system listed to UL 3741, a route to rapid shutdown inside the array boundary.
Specific yield
Annual AC energy per kW of DC rating.
STC
Standard test conditions: 1,000 W/m², 25 °C cell.

Formula sheet

Slope factor f = √(1 + s²); tilt θ = arctan s Module plan area A_plan = A_module ÷ f Coverage φ = Σ A_plan ÷ A_roof,plan; R329.6.2 threshold 0.33 Annual energy E = P_DC × H_POA × PR Opposite planes cos i_A + cos i_B = 2 cos β sin α_s (both sunlit) Cold open-circuit voltage V_oc,max = V_oc [1 + β_Voc (T_min − 25)]; n_max = floor(V_max ÷ V_oc,max) Circuit current I = 1.25 × I_sc Mismatch on one tracker Loss(r) = 1 − max(2r, 1) ÷ (1 + r); maximum 1/3 at r = 0.5 Marginal efficiency η_marg = η_solar→battery→home ÷ η_solar→home Storage break-even P_peak ÷ P_off-peak > 1 ÷ η_marg Arbitrage value ≈ E_evening × Σ days × (V_stored − V_alternative) Thermal store E_electric = Q_thermal ÷ COP Autonomy t = E_usable ÷ P_mean Busbar backfeed see Electrical · Busbar backfeed Attachment load F = spacing × rail spacing × w (w dead load or net uplift, psf) Point source L(d) = L(1 m) − 20 log₁₀ d

Array size and what it supports

Table 12 maps array size to production and to the share of the reference demand.

Table 12 Array size, production and share of the reference all-electric demand
ModuleskW DCPlan area, sfkWh/yr, all southkWh/yr, split planesSplit, share of demand
104.32046,8005,80036%
208.640814,00012,00072%
2510.851017,00015,00090%
3615.573525,00021,000129%
4820.697933,00028,000172%

430 W modules at 4:12, 1,600 kWh/kW due south; demand 16,000 kWh. Rows above 25 modules need both planes or the 36 in setback.

Figure color legend

Red: deficient, or fails the stated criterionAmber: marginal or conditionalGreen: meets the criterionGray: existing or baselineTeal: neutral quantity, reference line or annotation; never a grade

In Figure 1 red marks area the code reserves for pathways and amber the ridge setback whose width is conditional on coverage. In Figure 13 amber marks the bus the load-side rule limits.

Code points and inputs to confirm

Sources

Set v2 draft 1, 2026-10-23: rewritten as a generic theory guide to spec set v2 from the v1 guide (archived). Roof geometry moved to the spec's reference footprint; CRC sections renumbered to the 2025 cycle (R329, R330); storage aggregate limits corrected to CFC 1207.11 (40/80/100/200 kWh); the v1 structural exemption (a Washington amendment) replaced by the R329.4 load cases; rapid shutdown treated in Part 3; series and parallel mismatch separated; winter storage value conditioned on surplus; tracker current limits updated to the current class datasheet; orientation factors, opposite-plane summation and clipping computed from one irradiance model; thermal stores counted in electric-equivalent kWh; tariff values checked against the 2026 schedule; house values moved to the House Project Guide. Values from one script. Draft 1a: Lighting links repointed to the v2 guide.

↑ Back to top